Flatiron $42M Suit: SCDOT Delayed Project, Breached Contract
Flatiron $42M Suit: SCDOT Delayed Project, Breached Contract
Abstract
Flatiron Constructors is seeking $42 million in damages from the South Carolina Dept. of Transportation (SCDOT) The suit alleges that state mismanagement and foot-dragging on a project in Horry County caused the contractor to miss its initial deadline and incur millions in costs that it says amounts to a breach of contract. The state issued its notice to proceed in February 2014 with the initial requirement for substantial completion in 1,220 days, or about 40 months. The initial deadline would have been in 2017.